Who Uses This Feature
Before You Start
To use manufacturing you need:- Items set up for all raw materials, packaging materials, and finished products
- A Bill of Materials created for each finished product
- Workstations defined for each processing step
- Warehouses set up for raw material storage, work-in-progress, and finished goods
Step 1: Create a Bill of Materials (BOM)
The Bill of Materials (BOM) is the recipe for a product. It lists every input and every processing step needed to produce one unit of the finished product. Example: BOM for “Roasted Salted Cashews 250g”
Operations:
Creating the BOM
- Go to Manufacturing workspace → Bill of Materials → New
- Set the Item to the finished product (Roasted Salted Cashews 250g)
- Set the Quantity to 1 (one 250g pouch, the base unit)
- In the Raw Materials table, add each input with its quantity
- In the Operations table, add each processing step with the workstation and estimated time
- Click Submit and then set it as the Default BOM for this item

Step 2: Create a Production Plan (Optional)
If you are planning a large production run based on Sales Orders or a weekly forecast, use the Production Plan to calculate what needs to be made and whether you have sufficient raw materials.- Go to Manufacturing workspace → Production Plan → New
- Click Get Sales Orders to pull in all open orders for manufactured items
- The system calculates the required finished goods quantity
- Click Get Raw Materials to see what raw materials are needed
- The system flags any raw material shortages and can generate Material Requests to trigger purchasing
Step 3: Create a Work Order
A Work Order authorises and tracks a specific production run.- Go to Manufacturing workspace → Work Order → New
- Select the Item to produce
- Select the BOM (the system suggests the default BOM)
- Enter the Planned Quantity to produce
- Set the Planned Start Date and Planned End Date
- Set the Source Warehouse (raw material store) and Work-in-Progress Warehouse
- Set the Target Warehouse (finished goods store)
- Submit

Step 4: Issue Raw Materials to Production
Before processing can start, the Store Keeper transfers raw materials from the raw material warehouse to the Work-in-Progress (WIP) area.- Open the Work Order and click Transfer Materials
- The system pre-fills the Stock Entry with the required raw materials and quantities from the BOM
- Confirm the Batch Numbers for each raw material being transferred
- Submit the Stock Entry
Step 5: Record Production Progress with Job Cards
As production progresses through each workstation, Machine Operators update Job Cards to record what has been done.- Go to Manufacturing workspace → Job Card (or open from the Work Order)
- Open the Job Card for the current operation (e.g., Roasting)
- Enter the Start Time when the operation begins
- Enter the Completed Quantity as work progresses
- Enter the End Time when the operation is complete
- Submit

Step 6: Record Finished Goods and Receive into Warehouse
Once all operations are complete and the Work Order quantity is produced, the Store Keeper creates a Stock Entry to receive the finished goods.- Open the Work Order and click Finish
- The system creates a Stock Entry of type “Manufacture”
- The Source entries deduct the raw materials consumed
- The Target entry receives the finished goods into the finished goods warehouse
- Enter the batch number for the finished product
- Enter the expiry date for the finished batch (calculated from today + shelf life, or entered manually)
- Submit
Recording Machine Downtime
When a machine stops unexpectedly, the operator records a Downtime Entry to capture the reason and duration.- Open the relevant Job Card and click Record Downtime
- Enter the Start Time, Stop Reason, and Workstation
- When the machine is running again, enter the End Time and submit
Field Guide: Work Order
Reports for Manufacturing Monitoring
Cost of Production
The system captures the cost of each production run automatically:- Material cost: the value of raw materials consumed, taken from the stock valuation
- Operation cost: based on the time recorded in Job Cards and the operating cost per hour set on each Workstation
- Total cost per unit: calculated and available in the Work Order for pricing review
Best Practices
- Keep BOMs accurate and up to date. When a supplier changes the raw material density or you change the pack size, update the BOM before raising new Work Orders
- Always issue materials against a specific Work Order, not as a free-form Stock Entry. This keeps production costs accurate
- Record the expiry date on finished goods at the time of production receipt, not later. The batch’s shelf life clock starts from the production date
- Check the BOM Stock Report before starting a large Work Order to confirm raw material availability. Running out of packaging material mid-production wastes processing time
- Use the Plant Floor view during production hours so supervisors can spot stalled Job Cards without walking the floor
Troubleshooting
The system shows insufficient stock to finish the Work Order. Either the required raw materials were not issued from the correct source warehouse, or another Work Order is consuming the same batch. Check the Stock Ledger for the raw material item. The Work Order shows as In Process but no Job Cards are being updated. The Machine Operators may not be submitting Job Cards, or the Job Cards may have been created but not opened. Check the Job Card list filtered by Work Order. The finished goods are not appearing in the target warehouse after clicking Finish. The Stock Entry (Manufacture) may be in Draft status. Go to the Stock Entry linked to the Work Order and submit it.Related Features
- Items - Bill of Materials setup and finished goods item configuration
- Inventory Management - Raw material management and FEFO
- Quality Inspection - In-process and finished goods quality checks
- Procurement - Sourcing raw materials for production