A Work Order is the formal authorisation to manufacture a specific quantity of an item. It ties together the Bill of Materials, the production schedule, the material movements, and the quality checks required for a production run. Every production activity on the floor traces back to a Work Order.

Who Uses This Feature


Before You Start

Before creating a Work Order, ensure:
  • The item to be manufactured has an active, approved BOM
  • Raw materials are available (or will be by the planned start date)
  • Warehouses for raw materials, WIP, and finished goods are configured

Creating a Work Order

1

Open Work Orders

Go to the Manufacturing workspace and click Work Order from the Production card, or use the Work Order shortcut.
2

Create a new Work Order

Click New. Work Orders can also be created automatically from a Production Plan — in that case, skip to step 4 to review the auto-populated details.
3

Select the item to manufacture

In Item To Manufacture, select the finished product. The BOM No field automatically fills with the item’s default BOM.
4

Select or confirm the BOM

Confirm the BOM No is correct. If the item has multiple BOMs, select the appropriate one. The required materials table populates from the BOM.
5

Enter the quantity

In Qty To Manufacture, enter how many units to produce in this run.
6

Set the planned dates

Enter the Planned Start Date (mandatory) and the Planned End Date. These drive scheduling and the Production Planning Report.
7

Configure warehouses

  • Source Warehouse: Where raw materials will be drawn from (optional — defaults to the warehouse set in BOM)
  • Work-in-Progress Warehouse: Where materials are held during production
  • Target Warehouse: Where finished goods will be stored after production (mandatory)
  • Scrap Warehouse: Where scrap materials go (if applicable)
8

Review required items

The Required Items table shows all raw materials from the BOM scaled to your planned quantity. Check the quantities and source warehouses for each item.
9

Link to a Sales Order or Production Plan (optional)

If this Work Order is for a specific customer order, link it to the Sales Order. If it was created from a Production Plan, the Production Plan field is already populated.
10

Save and Submit

Click Save to review, then Submit to activate the Work Order. Status changes to Not Started.
Work Order form showing item, BOM, quantity, warehouse settings, and required materials table

After Submission: The Production Workflow

Once a Work Order is submitted, the production flow involves three main steps using Stock Entries.

Step 1: Transfer Materials to WIP Warehouse

Before production begins, transfer raw materials from the store to the WIP warehouse:
  1. Open the Work Order
  2. Click Transfer Raw Materials
  3. A Stock Entry of type “Material Transfer for Manufacture” is created
  4. The Store Keeper reviews and submits it
This updates the Work Order’s Material Transferred for Manufacturing quantity.
Work Order showing the Transfer Raw Materials button and material transfer progress

Step 2: Record Production (Job Cards)

If the BOM has operations, the system creates Job Cards for each operation. Operators work through the Job Cards on the floor, recording time and completed quantities. See Job Card for the full guide.

Step 3: Record Finished Goods

When production is complete, record the manufactured goods:
  1. Open the Work Order
  2. Click Finish (or create a Stock Entry from the Work Order)
  3. A Stock Entry of type “Manufacture” is created
  4. This entry:
    • Deducts raw materials consumed from the WIP warehouse
    • Adds finished goods to the target warehouse
    • Records any scrap
The Work Order’s Manufactured Qty field updates. When manufactured quantity equals the planned quantity, the Work Order status changes to Completed.

Field Guide


Work Order Status


Reports and Monitoring

Number Cards (Manufacturing Dashboard)

Dashboard Charts

Reports


Notifications and Alerts

There are no standard automated notifications on Work Orders by default. However, supervisors can monitor the status of all active Work Orders from the Work Orders in Progress report and the Work Order Analysis dashboard chart.

Best Practices

Always create Work Orders from a Production Plan. Creating Work Orders directly is possible, but the Production Plan ensures raw material requirements are verified first and coordinated purchasing happens before production starts. Use the correct planned dates. Accurate planned dates drive the Production Planning Report and help supervisors prioritise which Work Orders to start first when capacity is limited. Don’t submit a Work Order until materials are confirmed. A Work Order in Not Started status with no materials available will stall on the floor. Confirm material availability before submission. Record process loss accurately. If scrap or loss occurs, record it honestly in the manufacture Stock Entry. This is the only way to understand true material consumption and improve BOM accuracy over time. Use multi-level BOM for complex assemblies. If your product has sub-assemblies, always tick Use Multi-Level BOM to see the complete raw material requirement at the top level. Link Work Orders to Sales Orders. This creates traceability from a customer order to the production run that fulfilled it, which is critical for delivery tracking and customer communication.

Troubleshooting

“BOM not found” when creating a Work Order: The item does not have an active, submitted BOM. Create and submit a BOM first. Required Items table is empty: The linked BOM has no items in its materials table. Open the BOM and add raw materials. Can’t submit the Work Order: Check that all mandatory fields are filled: Item To Manufacture, BOM No, Qty To Manufacture, Planned Start Date, Company, and Target Warehouse. Manufactured Qty is not updating: Confirm that the manufacture Stock Entry (type: Manufacture) linked to this Work Order is in Submitted status. Work Order is stuck in Not Started: No Stock Entry of type “Material Transfer for Manufacture” has been submitted against it. Transfer the raw materials to start the Work Order.